Rooppur power reaches the grid at 3:16pm, 350MW in first phase
Photo: Collected
Tuesday, 3:16pm. In the presence of Science and Technology Minister Fakir Mahbub Anam, Rooppur, the country’s first nuclear power plant, began sending electricity to the national grid for the first time. After a long wait and a series of technical tests, 350 megawatts of electricity generated at the plant’s first unit was connected to the grid on a trial basis.
The moment is being seen as a major milestone on Rooppur’s path to generation and grid connection.
According to the set plan, electricity will flow to the grid for about 8 to 10 hours during this initial trial connection. During this time, several important technical tests will be carried out, including monitoring how the turbine and generator are running and how effective and stable the integrated operating system with the grid remains.
The plant will then be disconnected from the grid for further tests. After a break of about 28 hours, it will be connected to the grid again for 4 to 6 hours to complete the necessary technical and operational tests.
At each stage, the performance of the plant’s various systems, the efficiency of the turbine-generator and coordination with the national grid will be examined closely. If all the test results are satisfactory and the scheduled work of this stage is completed, approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) will be needed for the next round of trial operation.
If BAERA gives approval, the plant will again be connected to the grid on a trial basis and the next phase of supply will begin. Under the agreement with the Russian contractor, commercial power supply at full capacity from the first unit will begin only after 10 months of trial operation are completed.
Rooppur has two units, each with a generation capacity of 1,200 megawatts. The 2,400-megawatt plant as a whole is expected to play an important role in meeting the country’s growing electricity demand, ensuring energy security and sustainable generation.
The trial grid connection of the first unit is an important step in the progress of the country’s power and energy sector. With it, Bangladesh has stepped into a new phase of generating electricity with nuclear technology.
Background
Fuel loading at Rooppur’s first unit, scheduled for 7 April, had been suspended as the licence from the Bangladesh Atomic Energy Regulatory Authority had not been obtained, Ittefaq reported on 16 April.
The commissioning licence, that is, permission to load fuel into the reactor, was obtained on 16 April, Jugantor reported on 28 April. According to an Ittefaq report, loading of uranium nuclear fuel into the first unit formally began after 3pm on 28 April.
By the numbers
The plan was for electricity from the first unit to be connected to the national grid within at least three months of the start of fuel loading, Ittefaq reported on 18 April.